Solar park Dittersbach put into operation

Solar park Dittersbach put into operation

Frankenberg / Freiberg, December 16, 2020. The open-space photovoltaic system built by Sabowind in the Frankenberg district of Dittersbach was connected to the grid on December 16, 2020. The solar park with a total output of 8.3 MWp will now supply environmentally friendly electricity for around 2,200 households.

Within three months, more than 257 module tables with 24,598 modules were erected and assembled on an area of ​​around 7.5 hectares. The photovoltaic park generates 8,400,000 kWh of green electricity per year.

Sabowind operates and monitors the solar park.

The city of Frankenberg invited tenders for an unused commercial area for the construction of an open-space PV system, for which Sabowind was awarded the contract.