On 31st March 2014 Sabowind GmbH was issued the building permission for a wind turbine of the type Enercon E-53 with a total rated power of 800 kW, an hub height of 73,25 m and a rotor diameter of 52,9 m at the location Beiersdorf, a district of the community Fraureuth in the federal state of Saxony.
The construction works for the roads, the grid connection and the foundation will start in September. The turbine will be erected by December 2014 at the latest and will be put into operation afterwards. With the erection of this turbine Sabowind GmbH expands the existing wind park area in Beiersdorf to a total of 5 wind turbines.
The technical and commercial management of the turbine is applied by Sabowind Service GmbH, which is also located in Freiberg.
Building permission for location Beiersdorf