On 1st June 2015 the construction works started for the erection of two wind energy turbines of the type Enercon E-70 E4 with a total rated power of 2,3 MW each, a hub height of 64 m as well as a rotor diameter of 71 m at the location Rackwitz in the federal state of Saxony. On 29th April 2015 Sabowind GmbH received the building permission for the erection of the two turbines north of the town Leipzig.
Currently Sabowind implements the roads followed by land improvement measures as well as the construction of foundations and grid connection. The erection of the turbines as well as the commissioning is planned for August. With the erection of these two turbines the existing wind area is expanded to its optimum capacity of 22 turbines.
Sabowind Service GmbH takes over the technical management of both turbines.